Slack Time

The amount of time that a non-critical path activity can be delayed without delaying the project is referred to as slack time.

Let’s take a example to understand it better:

We have three tasks T1, T2, T3.

T1 takes 5 units of time and independent of any other task.

T2 takes 7 units of time and independent of any other task.

T3 takes 2 units of time and depends on both T1 and T2.

 

So the Slack Time for all tasks will be

T1: 2 units of time (T1 can get start 2 units of time late and still the process will complete in the specified time).

T2: 0. (It’s on the critical path!)

T3: 0.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s